Coogee Chemicals to Covalent Lithium Pipeline

Project Overview

This project involved the construction of a 4 km acid pipeline connecting Coogee Chemicals to Covalent Lithium’s processing facility. The works required chemically resistant materials, precision welding, and strict QA requirements.

Date Completed

Oct 2023–Apr 2024

Level Steel’s Scope of Work

  • Fabrication and supply of pipeline spools and components across the full 4 km alignment
  • Welding and dimensional inspection
  • QA documentation, coating compliance, and traceability

Technical & Quality Deliverables

  • Compliance with chemical-service welding and fabrication standards
  • Full material traceability and MDR delivery

Project Outcome

Level Steel delivered compliant, fit-for-purpose pipeline components supporting safe transport of process materials across the asset.